| Track welding taking place on the curve at Starr Gate on 22nd February |
Wednesday, 10 March 2021
Track Welding
Monday, 8 March 2021
All Change at Little Bispham
![]() |
| Flexity 016 waiting at Little Bispham, with a stop barrier blocking the northbound line |
![]() |
| Flexity 008 turning short at Little Bispham on Tuesday 2nd March |
![]() |
| Starr Gate bound Flexity 016 passing the track barrier at Little Bispham |
![]() |
| Flexity 012 entering the loop at Little Bispham on 6th March |
![]() |
| Flexity 016 entering Little Bispham turning circle on 6th March |
![]() |
| Flexity 017 passing the northbound track barrier at Little Bispham on 6th March |
![]() |
| Flexity 003 heading south out of the turning circle at Little Bispham on 2nd March |
![]() |
| Flexity 015 exiting the loop at Little Bispham on its way to Starr Gate |
Tuesday, 2 March 2021
Unimog 939
![]() |
| Unimog 939 returning to Starr Gate depot on 22nd February |
![]() |
| Unimog 939 attending to the overhead at Norbreck on 22nd February |
![]() |
| Unimog 939 on New South Promenade on 22nd February |
![]() |
| Unimog 939 working near Beach Road in Cleveleys on 1st March |
![]() |
| Unimog 939 with the snowbroom attachment fitted, towing Brush 634 in February 2016 |
![]() |
| The Unimog recovering 706 which had lost its trolley head, near Central Pier in September 2015 |
Monday, 1 March 2021
Tram service extended to Bispham
![]() |
| Flexity 012 entering the centre track at Bispham, with an orange barrier blocking the northbound line |
![]() |
| Flexitity 010 crew manually setting the points for the southbound line at Bispham |
![]() |
| Flexity 012 switching to the southbound line at Bispham |
![]() |
| Flexity 002 waiting on the centre track at Bispham, with the line to the north barricaded |
![]() |
| Flexity 012 terminating at Bispham while 010 awaits its departure time for Starr Gate |
![]() |
| Flexity 010 terminating on the centre road at Bispham before reversing direction |
Tuesday, 23 February 2021
Harrow Place to Cabin Tram Service
Service on the Blackpool Tramway was suspended from Sunday 14th February until Sunday 21st February due to engineering work. From Monday 22nd February until Saturday 27th February, a partial service between Harrow Place and Cabin will be in operation, due to ongoing engineering work continuing both north and south of this section of the tramway. Northbound trams used the crossover just beyond the Cabin tram stop to reverse, while southbound trams continued empty past Harrow Place to the crossover just north of Starr Gate tram depot to reverse.
Flexity 013 having crossed over to the northbound track, just north of Starr Gate tram depot
![]() |
| Flexity 008 crossing over at Cabin, notice the barriers on the northbound line |
![]() |
| Flexity 015 beginning its northbound run at Harrow Place on 22nd February |
![]() |
| Flexity 008 arriving at the southern terminus at Harrow Place |
![]() |
| The socially distanced seating arrangements in Flexity 013 |
![]() |
| Flexity 013 using the crossover to the north of Starr Gate tram depot on 22nd February |

Southbound Flexity 003 using the crossover near Starr Gate tram depot at 08:15 on 23rd February
![]() |
| Flexity trams 005 and 018 at the Cabin on 23rd February |
Thursday, 18 February 2021
Moving the Tamper from track to track
![]() |
| The Plasser tamper being loaded from the southbound line onto its transporter at Cabin |
The Plasser tamper currently in use in Blackpool was moved from the southbound to the northbound track today. The tamping machine failed to negotiate the crossover at the Cabin yesterday, due to it's long wheelbase and fixed (non-bogie) wheel arrangement. The only way to effect the transfer was to load the tamper onto its low-loader, move the truck across to the northbound line and unload it again.
![]() |
| The tamper and transporter lining up over the northbound track |
![]() |
| The Plasser tamper sat on its jacks after the transporter had been moved out of the way |
![]() |
| The tamping machine being lowered down on its hydraulic jacks |
![]() |
| The Tamper sat on the northbound line near Cabin, ready to continue work again |
Wednesday, 17 February 2021
Plasser Tamper on the Tramway
![]() |
| The Plasser 09/16 CAT ZW Tamper in action near Admiral Point |
![]() |
| Blackpool Transport Enviro 445 heading north past the tamping machine |
![]() |
| The Plasser tamper working its way south along Queen's Promenade |
![]() |
| A close-up of the complicated tamping machinery in operation |
![]() |
| The Plasser tamper working slowly southwards from Little Bispham |
![]() |
| A broadside view of the Plasser 09/16 CAT ZW Tamper in action |